The first investment of TGEC on gas projects is Parsi flare gas recovery.
CLIENT: NISOC
FEED GAS: 4 MMSCFD
NATURAL GAS RECOVERY: 2.8 MMSCFD
CONDENSATE RECOVERY: 50 TON/DAY
INSTALLED COMPRESSOR: 2 SET
CONSTRUCTION PERIOD: 2016-2017
OPERATION START: 2018