پروژه بازیابی گاز مشعل میدان نفتی عسلویه

Asalouye
 Flare Gas Recovery
subject
Gas Compression and Transmission Process
B.O.O Investment Contract Model
NIGC Investee
Tamkar Gas Equipment Co. Investor
Up to 6 MMSCFD Capacity
5 MMSCFD Natural Gas Recovery
Condensate Recovery
7 set Installed Compressor
 24 Months Construction Period
1403 Operation Start